Works on construction of the Highway on Vc Corridor started in mid-June 2012. Niskogradnja is in charge of the sub-section Zvirovići Kravice, which makes a 5-kilometer unit.
The value of the project is 120 million KM. At the international tender, this very important project was awarded to Niskogradnja doo and the Czech company OHL ŽS consortium. These two companies represent a well-played team of an international company with good reputation and the local operational company with experience.
Having in mind a high categorization of the roads, and the complexity of the ground in terms of relief, as well as the importance of the area in which this section runs, structures in the alignment and over it appear ( 2,00 km-long structures, i.e.1,50 km-long bridges and viaducts and 0,50 km of tunnels).
Structures designed on this alignment include the Međugorje interchange that connects the towns (Međugorje, Čitluk, Ljubuški,...) and regional roads in this part of Herzegovina, make the movement of vehicles easier and running of traffic safer. After this interchange, the following structures appear on the highway: Bituljani underpass (4,0m), Studenčica bridge (590,00m) across the river of the same name, Pavlovići viaduct (387,00m), Bijela Vlaka tunnel (485,697m), and Trebižat bridge (380,00) accross the Trebižat river.
By constructing of this section, people travelling to Croatia, religious people and pilgrims who visit Međugorje and the Holy Lady as well as other tourists will be able to reach their destination more quickly.
Works on extension of water supply system in the area of Tunjice will enable 90% of the population of this part of the town to be connected to the waterworks, and will also include extension and improvement of the waterworks network.
The beginning of works is on 19 April 2012; this project represents one of the biggest after-war investments of Banja Luka City. Niskogradnja doo Laktaši, is in consortium with the German company Ludwig Pfeiffeer GmBH and Hidrokop doo, until the completion in these parts of the city. As part of Niskogradnja doo tasks, we can highlight laying of the pipelines, installing of the water tank, pump station and booster pump station.
Mounting manholes, valves, fittings, in the total length of about 6.2 km. Then, constructing secondary pipelines for water supply, including the house connections (650 pieces) in the total length of about 16.2 km. Constructing two concrete tanks, with 3000 m3 and 7500 m3 of volume, constructing the pump station and booster pump station.
The deadline for completion of works is twenty to twenty-nine months.
Investor: Banja Luka City
Contractors: Consortium „Ludwig Pfeiffer GmBH" / „Niskogradnja" / „Hidrokop"
Value of agreed works: 17.500.000 Euro